02 - PERFORMANCE CAMBRIDGEPORT.NET - PAGE 14 HOW FAST IT SHIPS GUARDIAN 10-12 WEEK COMMITMENT 35-725 kW classes, release-to-ship RELEASE Submittal Approved WEEKS 1-2 Final Engineering | Long-leads pulled from allocation WEEKS 3-8 Fabrication | Coil Set | Fan Array Assembly WEEKS 9-10 Controls Integration | Run Test | Leakage Proof WEEKS 10-12 Ship Release-to-ship, defined: the clock starts at approved submittal and release for production. Firm dates quoted at selection, before the PO — guaranteed against secured supply, not best efforts. WHERE THE INDUSTRY’S MONTHS ACTUALLY GO Strip apart any competitor's CRAH lead time and three long-leads dominate: fans, coils, controls. The rest is ~8 weeks of factory throughput. Twelve-month quotes aren't twelve months of work — they're a build queued behind components ordered after the PO landed. TYPICAL INDUSTRY QUOTE GUARDIAN | ON ALLOCATION WAITING ON FANS | COILS | CONTROLS - 4-9 MONTHS BUILD ~8 WEEKS SHIP PULL FROM STOCK BUILD - TEST SHIP WEEK 10-12 MONTHS RETURNED TO YOUR SCHEDULE